In 2024, Rosseti South will invest 4.6 billion rubles in the development of the energy complex in the regions of the company activity.

18.01.2024

Rosseti South plans to allocate 4,6 billion rubles for the implementation of the investment program in 2024. This amount of investment will allow to construct 554 km of power transmission lines and put power facilities with a total capacity of 88 MVA into operation in the regions of the company’s operation.
Thus, 2.7 billion rubles will be allocated for the development of the energy complex of Rostov Oblast. 279 km of power transmission lines and transformers with total capacity of 38 MVA will be built and reconstructed by the power engineers in this region.
686 million rubles are expected to transfer to Volgograd Oblast, and will be used to build and upgrade 74 km of transmission lines and substations with a total capacity of 4 MVA.
The amount of funding for the program in Astrakhan Oblast will be 973 million rubles. Work schedule in the region includes the construction and reconstruction of 144 km of power lines and transformers with total capacity of 45 MVA.
57 km of transmission lines and 1 MVA substations will be built in Kalmykia. The investments are estimated at 283 million rubles.
Construction of facilities for technological connection of preferential energy consumers category will continue this year. 1.7 billion rubles will be allocated for these purposes. At the request of beneficiaries, 288 km of power transmission lines will be built and transformer stations with the capacity of 27 MVA will be provided to fulfill the company's obligations.
The implementation of Rosseti South's investment program will create the conditions necessary to ensure the capacity of power grids, to make utility connections, and to maintain the operational readiness of equipment required for a reliable, uninterrupted, and high-quality power supply to consumers.